July 31, 2025
Site demolition has been completed, site cuts have continued, and the building pad has been established. Crews have also begun mobilizing facilities and setting up laydown areas. In the coming weeks, work will include applying stone to the building pad, laying out geo-piers, and beginning pier and foundation work. Crews will also start installing CMU (Concrete Masonry Units) and move forward with site utilities, including temporary electric and water service.
Traffic Notice:
Starting Monday, August 11, the lane closest to the fire station heading east on Second Street will be closed for approximately 3–4 weeks to accommodate construction. Please use caution in the area and allow extra travel time.